Reference No: 0012
Company: ISG PEARCE
Site Responsible Person: Lee Sanders
Tel. No: 0808 166 2175
Site Location: Netto Coventry Jubilee Crescent.
Names of Personnel on Site: Mark Fleetwood, Mark Reeves, Hugh Maguire & Richard Waters.
Start Date: 20th July 2011
Finish Date: 1 weeks from start date.
Vinyl Installation
Vinyl works involving prepping sub floor. This includes clean & sweep making it ready for Latex screed. The following sequence of work applies:
SEQUENCE OF EVENTS / MODE OF OPERATION
| Task No. | Description | Day | Date | Responsible Person |
|---|---|---|---|---|
| 1 | Site inspection | Day 1 | 19/07/2011 | L.Sanders |
| 2 | Risk assessment | Day 1 | 20/07/2011 | M.Reeves |
| 3 | Material supply | Day 2 | 20/07/2011 | L.Sanders |
| 4 | Installation | 1 weeks from start date | 27/07/2011 |